Weekly Update, Week Ending March 13, 2020

Posillico Environmental, Inc (Posillico), National Grid’s Remediation Contractor is tentatively scheduled to remobilize to the Site during the week of March 23, 2020 to complete the construction activities associated with the Site remedy.

The remaining activities include completing installation of the crushed stone Site cover and asphalt pavement Site Cover, construction of permanent stormwater swale, installation of a new perimeter fence.

General hours of operation will be Monday through Friday, 7:00 AM to 4:00 PM.