Site Remedy Completed November 6 2020

Posillico Environmental, Inc. (Posillico), completed the remedy implementation on both the on-site and off-site properties. The final activities completed included installation of the asphalt pavement cover, construction of the post-remediation stormwater management system, and installation of the perimeter fence. Crack monitoring gauges were removed, construction equipment was demobilized. A final site inspection was conducted with National Grid.

Brown and Caldwell Associates, National Grid’s Project Engineer, will prepare the final documentation for the Site which includes the Final Engineering Report and the Site Management Plan. These documents will be submitted to NYSDEC for their approval. An Environmental Easement will also be established for the Site and the Off-Site Property, as required by the NYSDEC.